Sewage Pump Selection Checklist for Contractors

2026-11-055 min readSelection Guide

Six measurements, five questions and four site checks before you order. A field checklist for contractors who cannot afford a wrong specification.

A wrong specification is not discovered at commissioning. It is discovered three months later, on a call-back, at your cost. And it is almost always the same six mistakes.

This is a field checklist, not a theory piece. Six measurements, five questions to the client, four site checks, and an order form you can copy.

It works for any wastewater pump station — from a single sewage lifting device under a basement floor to a sewage pumping system serving several dwellings. The measurements change; the sequence does not.


Before you leave the office

ItemWhy
Confirm whether it is black water or grey waterChanges free passage, impeller type and materials
Confirm the platform — 220–240 V / 50 Hz or 110 V / 60 HzNot interchangeable
Confirm who supplies the control panelAvoids a missing component on install day
Confirm the delivery lead time against the programmeA station that arrives late stops the job

Six measurements to take on site

Take all six before you order. Missing one is how a specification goes wrong.

#MeasurementHow
1Static liftFrom the pump start level to the highest point of the discharge
2Discharge route lengthIncluding horizontal run and vertical rise, measured not estimated
3Bend and fitting countEvery bend, valve and reducer adds equivalent length
4Available fall to the stationFrom the lowest fixture outlet to the station inlet, minus the trap
5Inlet pipe sizeExisting or planned — do not reduce it
6Available spaceFootprint, height to the lid, and clearance for servicing

Then calculate the total dynamic head from 1, 2 and 3. If the figure is close to the pump's shut-off head, the selection is marginal and the next size up is the safer choice.

Method: how to calculate total dynamic head.


Five questions to the client

These are the questions that change the specification and that clients do not volunteer.

QuestionWhy it matters
Who will use this?A family, tenants, the public or customers — each needs a different free passage
Will wipes go down?The honest answer is always yes. 50 mm free passage, not 40
Is there a kitchen or laundry on this line?Grease and lint change the impeller choice
Who maintains it after handover?If the answer is "nobody", specify differently
Is the building occupied during the work?Affects the isolation strategy and the programme

The maintenance question is the one worth asking twice. A station specified for a client who will not maintain it needs a bigger free passage, a larger tank and an alarm — not a cheaper unit.


Four site checks

CheckWhat you are looking for
Vent routeA genuine path to outside air at full bore. If there is none, the job has a design problem no equipment solves
PowerIsolator position, circuit capacity, RCD, cable route to the tank
AccessCan the lid be reached and lifted without moving anything? Can the pump be lifted out?
Water table / ground conditionsIf the station is buried, is there groundwater? Does it need a drainage layer?

The vent is the check that stops jobs. If there is no route, resolve it before ordering — not after the station is on site and the client is asking why the room smells.


The order form

Copy this. It is the difference between a specification and a guess.

Project / address:
Date:
Contractor:

DUTY
  Application ([basement drainage](/applications/basement-bathroom) / kitchen / flat / commercial / other):
  Water type (black / grey / mixed):
  Fixtures served:
  Occupants or users:

HYDRAULICS
  Static lift (m):
  Discharge route length (m):
  Bends and fittings (count):
  Total dynamic head (m):
  Required flow (m³/h):
  Discharge bore available (mm):
  Inlet bore (mm):

STATION
  Free passage required (mm):
  Impeller preference:
  Tank volume required (L):
  Working volume required (L):

ELECTRICAL
  Voltage / frequency:
  Control panel supplied by:
  Alarm required (Y/N):
  Remote signal required (Y/N):

SITE
  Vent route confirmed (Y/N):
  Lid access confirmed (Y/N):
  Groundwater present (Y/N):

DELIVERY
  Required on site by:

A buried lifting station selection guide is only useful if it is filled in. This form forces the six measurements and the five client answers onto one page, which is where they belong.


The six mistakes that cause call-backs

MistakeWhat happens
Sizing on static lift, ignoring frictionPump runs outside its curve, flow is poor, motor overheats
Free passage too smallBlocks on the first wipe; call-back within months
Tank too small for the fixturesShort cycling; float and motor wear out early
No vent, or an air admittance valveOdour, permanently; the client blames the pump
Discharge bore reduced to suit existing pipePump pushed off its duty point; overheating
Non-return valve not accessibleNever cleaned, fails, backflow, second call-back

None of these are equipment faults. All six are visible at the specification stage if the checklist is used.


Handover, so there is no second visit

ItemWhy
Start and stop levels written downSo the next person can check them
Model code and serial numberFor spares and warranty
Isolator location shown to the clientSo they can switch it off in an emergency
What the alarm means, and what to doThe most common call-out is a float the client could have freed
What must not go down the drainWipes, fat, sanitary products
Maintenance intervalsMonthly float test, annual impeller check

A laminated card next to the panel with those six points prevents more call-backs than any technical improvement.


Working on a real project?

Send the fixture list, not the model code

Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.

FAQ

What do I need to measure before ordering a sewage lifting station? Six things: static lift, discharge route length, bend count, available fall to the station, inlet pipe size and available space. Then calculate total dynamic head from the first three.

What free passage should I specify? 50 mm for any domestic installation serving general occupants, because wipes will arrive. 40 mm only where you control who uses it. Commercial and public duties need 50 mm or more.

How do I know if the pump is oversized? Plot the duty point on the curve. If it sits well to the left of the efficient area, the pump is oversized — it will short cycle and waste energy.

What is the most common specification mistake? Sizing on static lift and ignoring friction. On a long run in a small bore, friction can exceed the vertical lift, and the pump ends up outside its curve.


Next step

Send the completed order form and we will confirm the model, the free passage, the tank volume and the control arrangement — or tell you if the duty needs a different impeller than the one you expected.

Request a quotation · Calculate total dynamic head · See the range


Still unsure? Message the engineer on WhatsApp.

Models referenced in this note