Six measurements, five questions and four site checks before you order. A field checklist for contractors who cannot afford a wrong specification.
A wrong specification is not discovered at commissioning. It is discovered three months later, on a call-back, at your cost. And it is almost always the same six mistakes.
This is a field checklist, not a theory piece. Six measurements, five questions to the client, four site checks, and an order form you can copy.
It works for any wastewater pump station — from a single sewage lifting device under a basement floor to a sewage pumping system serving several dwellings. The measurements change; the sequence does not.
Before you leave the office
| Item | Why |
|---|---|
| Confirm whether it is black water or grey water | Changes free passage, impeller type and materials |
| Confirm the platform — 220–240 V / 50 Hz or 110 V / 60 Hz | Not interchangeable |
| Confirm who supplies the control panel | Avoids a missing component on install day |
| Confirm the delivery lead time against the programme | A station that arrives late stops the job |
Six measurements to take on site
Take all six before you order. Missing one is how a specification goes wrong.
| # | Measurement | How |
|---|---|---|
| 1 | Static lift | From the pump start level to the highest point of the discharge |
| 2 | Discharge route length | Including horizontal run and vertical rise, measured not estimated |
| 3 | Bend and fitting count | Every bend, valve and reducer adds equivalent length |
| 4 | Available fall to the station | From the lowest fixture outlet to the station inlet, minus the trap |
| 5 | Inlet pipe size | Existing or planned — do not reduce it |
| 6 | Available space | Footprint, height to the lid, and clearance for servicing |
Then calculate the total dynamic head from 1, 2 and 3. If the figure is close to the pump's shut-off head, the selection is marginal and the next size up is the safer choice.
Method: how to calculate total dynamic head.
Five questions to the client
These are the questions that change the specification and that clients do not volunteer.
| Question | Why it matters |
|---|---|
| Who will use this? | A family, tenants, the public or customers — each needs a different free passage |
| Will wipes go down? | The honest answer is always yes. 50 mm free passage, not 40 |
| Is there a kitchen or laundry on this line? | Grease and lint change the impeller choice |
| Who maintains it after handover? | If the answer is "nobody", specify differently |
| Is the building occupied during the work? | Affects the isolation strategy and the programme |
The maintenance question is the one worth asking twice. A station specified for a client who will not maintain it needs a bigger free passage, a larger tank and an alarm — not a cheaper unit.
Four site checks
| Check | What you are looking for |
|---|---|
| Vent route | A genuine path to outside air at full bore. If there is none, the job has a design problem no equipment solves |
| Power | Isolator position, circuit capacity, RCD, cable route to the tank |
| Access | Can the lid be reached and lifted without moving anything? Can the pump be lifted out? |
| Water table / ground conditions | If the station is buried, is there groundwater? Does it need a drainage layer? |
The vent is the check that stops jobs. If there is no route, resolve it before ordering — not after the station is on site and the client is asking why the room smells.
The order form
Copy this. It is the difference between a specification and a guess.
Project / address:
Date:
Contractor:
DUTY
Application ([basement drainage](/applications/basement-bathroom) / kitchen / flat / commercial / other):
Water type (black / grey / mixed):
Fixtures served:
Occupants or users:
HYDRAULICS
Static lift (m):
Discharge route length (m):
Bends and fittings (count):
Total dynamic head (m):
Required flow (m³/h):
Discharge bore available (mm):
Inlet bore (mm):
STATION
Free passage required (mm):
Impeller preference:
Tank volume required (L):
Working volume required (L):
ELECTRICAL
Voltage / frequency:
Control panel supplied by:
Alarm required (Y/N):
Remote signal required (Y/N):
SITE
Vent route confirmed (Y/N):
Lid access confirmed (Y/N):
Groundwater present (Y/N):
DELIVERY
Required on site by:
A buried lifting station selection guide is only useful if it is filled in. This form forces the six measurements and the five client answers onto one page, which is where they belong.
The six mistakes that cause call-backs
| Mistake | What happens |
|---|---|
| Sizing on static lift, ignoring friction | Pump runs outside its curve, flow is poor, motor overheats |
| Free passage too small | Blocks on the first wipe; call-back within months |
| Tank too small for the fixtures | Short cycling; float and motor wear out early |
| No vent, or an air admittance valve | Odour, permanently; the client blames the pump |
| Discharge bore reduced to suit existing pipe | Pump pushed off its duty point; overheating |
| Non-return valve not accessible | Never cleaned, fails, backflow, second call-back |
None of these are equipment faults. All six are visible at the specification stage if the checklist is used.
Handover, so there is no second visit
| Item | Why |
|---|---|
| Start and stop levels written down | So the next person can check them |
| Model code and serial number | For spares and warranty |
| Isolator location shown to the client | So they can switch it off in an emergency |
| What the alarm means, and what to do | The most common call-out is a float the client could have freed |
| What must not go down the drain | Wipes, fat, sanitary products |
| Maintenance intervals | Monthly float test, annual impeller check |
A laminated card next to the panel with those six points prevents more call-backs than any technical improvement.
Working on a real project?
Send the fixture list, not the model code
Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.
FAQ
What do I need to measure before ordering a sewage lifting station? Six things: static lift, discharge route length, bend count, available fall to the station, inlet pipe size and available space. Then calculate total dynamic head from the first three.
What free passage should I specify? 50 mm for any domestic installation serving general occupants, because wipes will arrive. 40 mm only where you control who uses it. Commercial and public duties need 50 mm or more.
How do I know if the pump is oversized? Plot the duty point on the curve. If it sits well to the left of the efficient area, the pump is oversized — it will short cycle and waste energy.
What is the most common specification mistake? Sizing on static lift and ignoring friction. On a long run in a small bore, friction can exceed the vertical lift, and the pump ends up outside its curve.
Next step
Send the completed order form and we will confirm the model, the free passage, the tank volume and the control arrangement — or tell you if the duty needs a different impeller than the one you expected.
Request a quotation · Calculate total dynamic head · See the range
Related reading
- Calculate total dynamic head — the calculation the checklist depends on
- Fixture unit method for sizing — how to size from the fixtures instead of guesswork
- How to choose tank volume — working volume, not nominal volume
- How to choose discharge pipe diameter — where friction loss is decided
- How many fixtures can one station serve — the question that comes up on every shared building
Still unsure? Message the engineer on WhatsApp.