Replacing a station is mostly a question of what you can reuse. Tank, connections, discharge and electrics each have their own rule. Step by step, with a reuse checklist.
Replacing a lifting station is not difficult. The part that decides whether it takes two hours or two days is what you can reuse — the tank, the inlet connections, the discharge pipe and the electrical supply each have their own rule, and getting them wrong is what turns a swap into a rebuild.
So before ordering anything, answer four questions. They determine the specification of the replacement, and they determine whether the job is a pump swap or a full station replacement.
Before you order: four questions
| Question | Why it matters |
|---|---|
| Is the tank sound? | If yes, you may only need the pump. If no, the whole station goes. |
| What head and flow does the installation actually need? | A like-for-like swap repeats the original mistake if the original was undersized. |
| Are the inlet positions compatible? | A new tank with inlets in different places means reworking the drainage. |
| What is the discharge bore and where does it run? | Determines whether the new pump's outlet will connect without adaptors. |
Do not order on the model code alone. Model codes change, ranges are discontinued, and the number on the old pump may not correspond to anything currently available. Order on head, flow, tank volume and connection sizes.
Reuse decision table
| Component | Reuse if | Replace if |
|---|---|---|
| Tank | Structurally sound, no cracks, lid seals, inlets in usable positions | Cracked, deformed, lid warped, inlets in the wrong place for the new layout |
| Pump | Only the pump has failed and the tank is fine | Tank also failed, or the pump was undersized |
| Non-return valve | Under 5 years old and holding | Any doubt — it is inexpensive and it is the most common cause of a repeat callout |
| Discharge pipe | Correct bore, no scale, accessible | Undersized, scaled, or buried with no access |
| Isolation valve | Operates freely | Seized or weeping |
| Float switches | Under 5 years old and tested | Any float showing water ingress or pitting |
| Control panel | Correct rating, terminals sound | Corroded, undersized, or no high-level alarm provision |
| Electrical supply | Correct voltage, protection and cable size | Undersized cable, no RCD, no isolator at the tank |
| Alarm | Working and audible from the occupied space | Absent — fit one during the replacement |
The general rule: reuse the civil works, replace the wet-end components. Anything that has been in contact with sewage for years is cheap to replace now and expensive to replace later.
Step 1: isolate and make safe
- Switch off at the isolator and lock it off. Not just at the control panel.
- Close the inlet if there is an isolation valve. If there is not, accept that flow will continue and plan for it.
- Pump or bail the tank down. A wet vacuum or a portable pump is faster than a bucket.
- Ventilate the space before opening the tank. Sewage gas accumulates in basements and confined chambers.
- Wear gloves, eye protection and a respirator if the tank has been standing.
Hydrogen sulphide is the hazard that gets underestimated. It is heavier than air, it collects at the bottom of the tank, and at low concentrations it deadens the sense of smell before it becomes dangerous.
Step 2: disconnect
Work in this order, because each step gives you access to the next:
- Electrics — photograph the terminal arrangement before disconnecting anything. Label the cores.
- Alarm and float cables — trace them back to the panel; do not cut.
- Discharge connection — usually a threaded union or a flexible coupling.
- Inlet connections — the most time-consuming part. Note the pipe material and diameter.
- Pump lifting — by the handle, never the cable.
- Tank fixings — floor anchors or a bedding layer.
Photograph everything before you take it apart. A phone photo of the terminal block and the inlet arrangement saves more time than any manual.
Step 3: check the new station against the opening
Before lowering anything in, dry-fit the new station.
| Check | What to confirm |
|---|---|
| Tank footprint | Fits the opening and leaves access to the lid |
| Tank height | Lid sits flush with the finished floor |
| Inlet heights | Match the incoming drains, or can be adapted |
| Inlet diameters | Match the pipe sizes present |
| Discharge outlet | Aligned with the existing riser |
| Cable length | Reaches the control panel without tension |
| Pump lifting height | Pump clears the tank base for servicing |
If the inlet heights do not match, the fix is a new inlet cut in the tank wall — not a flexible adaptor with an offset, which will hold solids.
Step 4: install
- Bed the tank on a level base. A tank on an uneven floor stresses the body when full.
- Connect the inlets, with a fall of at least 1 in 60 into the tank, and no low point between the fixture and the tank.
- Fit a new non-return valve on the discharge, close to the pump outlet.
- Fit an isolation valve above the non-return valve if there is not one already.
- Connect the discharge, with the correct bore for the pump's outlet — do not reduce it.
- Wire the pump, floats and alarm to the panel, matching the manufacturer's diagram.
- Fit the vent and confirm it terminates outside, above the flood level, and is clear.
- Fit the lid with a new gasket, tightened evenly.
The non-return valve and the vent are the two components most often skimped during a replacement, and the two most likely to bring you back.
Step 5: commission
Do not hand the station over after a single test run. Run it properly.
| Test | Pass criterion |
|---|---|
| Fill test | Pump starts at the designed start level |
| Stop test | Pump stops at the designed stop level, tank emptied |
| Alarm test | Lift the alarm float by hand; alarm sounds |
| Backflow test | No water returns to the tank after the pump stops |
| Leak test | No weeping at the inlets, lid, glands or discharge |
| Current test | Measured current at or below the rating plate |
| Cycle test | Three complete cycles with no fault |
The full sequence is in how to test a lifting station after installation.
Step 6: dispose of the old unit
- Drain it fully before moving it. A pump full of sewage is heavy and messy.
- Do not tip it into a drain — the tank contents go to a treatment point, not back into the system.
- Separate the materials: pump and motor as electrical waste, tank as plastic or steel, seals and gaskets as general waste.
- Clean and store the old pump if it may serve as a spare. A pump that failed on a blockage is often still serviceable.
Common mistakes
| Mistake | Consequence |
|---|---|
| Reusing the old non-return valve | Repeat backflow within months |
| Reducing the discharge bore to suit an existing pipe | Pump runs outside its duty, overheats |
| Reusing the old floats | Erratic level control, short cycling |
| Not fitting a high-level alarm | First warning is a flood |
| Connecting the vent to the soil stack without checking | Sewage gas in the room |
| Ordering on model code rather than duty | Same undersizing repeated |
Working on a real project?
Send the fixture list, not the model code
Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.
FAQ
Can I replace just the pump and keep the tank? Yes, if the tank is sound and the inlets are usable. This is the cheapest and quickest option, and it is common where the pump has failed but the civil works are fine.
Do I need to replace the non-return valve at the same time? Yes. It is inexpensive, it is the most common cause of repeat callouts, and it is much harder to reach once the station is back in service.
How long does a replacement take? A pump-only swap is a few hours. A full station replacement with new inlets and a new discharge is one to two days, plus drying time if the floor is made good.
Do I need a like-for-like replacement? No, and often you should not. If the old unit blocked repeatedly or ran constantly, the specification was wrong. Replace on measured head and flow, not on the old model code.
Next step
Send the model code of the existing station, the measured lift and the discharge bore, and we will confirm what fits the existing opening and what the correct rating is for the actual duty.
Request a quotation · Commissioning checklist · See the range
Related reading
- How to install a sewage lifting station — the first installation, as opposed to a swap
- How to fit a non-return valve on a vertical discharge — the component most often skimped during a replacement
- How to fit a high-level alarm — fit one while the station is open
- Drilling and sealing pipe penetrations in a basement — if the new unit needs a different discharge route
Still unsure? Message the engineer on WhatsApp.