A lifting station must vent to outside air at full bore. Here is how to size, route and terminate the vent — and why an air admittance valve will not do.
A external lifting station is vented by connecting the tank lid vent outlet to a dedicated pipe that runs to outside air at full bore, terminating above the roofline or through an external wall with a suitable terminal. The vent must let air in when the pump empties the tank and let gas out when wastewater flows in. It is not a pressure-relief detail — it is the mechanism that keeps sewer gas out of the building and stops the pump fighting a partial vacuum.
Getting it right is straightforward, and getting it wrong is the single most common reason a station smells. This guide covers sizing, routing, termination and the mistakes that come up repeatedly on site.
Why the vent is not optional
Three things happen inside a sealed tank that has no vent:
On fill. Wastewater entering displaces air. In an unvented tank that air has to go somewhere, and it goes out through the weakest path — usually the lid gasket, the inlet pipe joint or back up through a fixture trap. That is why an unvented station often smells worst immediately after a flush.
On empty. The pump removes water and, without replacement air, creates a partial vacuum. The pump then works against a negative pressure it was never sized for, flow drops, and the motor runs further up its curve than the duty point suggests.
Continuously. Anaerobic digestion of the sludge layer produces hydrogen sulphide and methane whether the pump runs or not. With no vent, those gases migrate into the room.
A vent solves all three. An air admittance valve solves only the second one.
Why an air admittance valve is not a substitute
Air admittance valves (AAVs) are common on drainage systems and frequently fitted to lifting stations by installers who treat the station like any other branch. They are one-way devices: they open to admit air when there is negative pressure, and close to prevent gas escaping.
That is precisely the wrong behaviour for a tank. The tank's problem is that it produces gas which must leave. An AAV holds that gas in until it escapes somewhere worse.
Use an AAV nowhere on a lifting station vent. Use it on fixture branches if you need to, but not on the tank.
Step 1: Identify the vent connection
On a packaged station the vent outlet is a spigot on the lid, separate from the inlet and the discharge. It is usually the smallest of the three connections and is often capped for transport — check that the cap has actually been removed, because a station that "smells despite a vent" is sometimes a station whose vent cap is still in place.
If the station has no dedicated vent outlet, the lid must be modified or a vent taken from the tank top through a sealed boss. Do not vent through the inlet pipework.
Step 2: Size the vent
The vent must be full bore for the station's rated vent connection — do not neck it down to fit through a joist or a wall.
A few practical rules:
- Do not reduce diameter anywhere along the run. Every reduction adds resistance and every resistance point is where condensate lifting pump and debris collect.
- Avoid long horizontal runs. If a horizontal section is unavoidable, keep it short and give it a continuous fall back toward the tank so condensate drains in rather than sitting in the pipe.
- No dips or sagging. A low point in a vent run fills with condensation and effectively closes the pipe. This is the second most common cause of a vent that exists but does not work.
Step 3: Route it
The route should go up and out. Two acceptable termination strategies:
| Strategy | How it works | Notes |
|---|---|---|
| Vertical to above roofline | Vent rises inside the building and terminates above the roof with a suitable cowl or terminal | Best performance; requires a clear vertical path |
| Through external wall | Vent exits through the wall with a suitable terminal, ideally with a short vertical rise outside first | Easier retrofit; check the terminal position carefully |
Terminal position rules that matter:
- Keep the terminal away from windows, doors, air intakes and openable roof lights. The general guidance in most codes is at least 3 m horizontally from an openable window — check the local requirement, because it varies.
- Do not terminate under a soffit, in a lightwell, in a roof void or in a garage. Gas will find its way into the building.
- Terminate above the level of the highest fixture connection so that the vent does not act as a drain.
- In cold climates, use a terminal that resists frost closure, and consider increasing the diameter for the exposed section.
Step 4: Connect to the drainage venting system
Where the station serves fixtures that already connect to a soil stack, the question is whether the station vent can share that stack.
The short answer: it can, provided the stack is a true vented stack running to outside air at full bore, and the connection is made above the highest fixture connection on that stack. What you must not do is connect the station vent into a stack that terminates in an AAV, or into a stack that is acting as a drain only.
If in doubt, run the station vent independently. A separate vent costs a length of pipe and removes an entire class of fault.
Step 5: Seal everything
The vent is only as good as the joints around it. Check:
- The vent spigot joint at the lid. Solvent weld or a proper mechanical seal, not tape.
- The lid gasket. A gasket that has been twisted during a service visit will leak, and the vent will not compensate.
- The cable gland. Oversized glands leave a continuous small gap.
- The inlet grommet. Frequently the actual leak point when the lid is sound.
A station with a good vent and a leaking lid gasket will still smell — the vent removes gas from the tank, but gas escaping past the gasket never reaches the vent.
Commissioning check
After installation, before handing over:
| Check | Pass criteria |
|---|---|
| Vent cap removed | Air flows freely at the terminal |
| Vent continuity | No dips, no reductions, no blocked terminal |
| Terminal position | Away from windows and intakes, above fixture level |
| Lid seal | No detectable leak with a fixture running |
| Pump cycle | Tank does not gurgle or pull air through traps |
| Trap refill | Every connected fixture trap holds water |
The trap check is easy to skip and matters: a dry trap in an unused basement shower will produce a smell that looks exactly like a station fault.
Common mistakes, ranked by frequency
- No vent at all. Still happens on retrofits where the installer treated the station as a sealed appliance.
- AAV instead of a vent. Solves gurgling, not gas.
- Vent terminated in the roof void. Gas enters the building at ceiling level.
- Vent reduced to fit through a joist. Undersized and prone to blockage.
- Horizontal run with a dip. Condensate closes the pipe within a season.
- Vent cap left on from transport. The vent exists on paper only.
- Shared connection to a stack with an AAV. No path to outside air.
If the station already smells and the vent looks correct
Work through the other causes before re-piping: lid gasket, non-return valve passing, sludge accumulation, and dried-out fixture traps. A structured sequence is in our guide to why a lifting station smells and in the maintenance notes on the product pages.
Venting solves the gas path. It does not solve a tank that is generating far more gas than it should because it has never been cleaned.
Working on a real project?
Send the fixture list, not the model code
Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.
FAQ
Can I vent a lifting station through the wall instead of the roof? Yes, provided the terminal is positioned away from windows, doors and air intakes, and the vent does not act as a drain. Many retrofits use a wall terminal with a short external rise.
Can a lifting station share a vent with a soil stack? It can share a genuinely vented stack that terminates in outside air, with the connection taken above the highest fixture. It must not share a stack that terminates in an air admittance valve.
How big should the vent pipe be? Match the station's vent connection at full bore throughout. Do not reduce the diameter to make the route easier.
Does the vent need to go above the roofline? Not always — a correctly positioned external wall terminal can be acceptable. What it must not do is terminate anywhere the gas can re-enter the building.