Testing a Lifting Station After Installation

2026-11-056 min readInstallation and Commissioning

Commissioning is eleven checks in three stages — before filling, on first run, and over three full cycles. The record sheet is what protects you later.

Commissioning a lifting station is not one test. It is eleven checks in three stages: before you fill the tank, on the first run, and over three complete cycles. Skipping the pre-fill stage is what turns a two-hour job into a return visit, because every fault you find after filling has to be found through water.

The output of the process is not "it works". It is a record — start level, stop level, run time, current draw, discharge flow. That record is what tells you in two years whether the pump has degraded or whether it was always like that.


Stage 1: before filling

Do all of these with the tank dry and the power off.

#CheckPass criterion
1Tank level and beddingLevel in both directions, no rocking, sitting flat on its base
2Inlet connectionsSealed, correct fall, no low point between fixture and tank
3Discharge connectionTight, correct bore, no reduction
4Non-return valve orientationArrow points away from the pump
5Isolation valveOperates freely, fully open
6FloatsFree to travel, not fouled on pipework or cable, set at the design heights
7VentClear, terminates outside, above flood level, no low point
8Lid gasketSeated, lid tightened evenly
9Electrical terminationsCorrect per the manufacturer's diagram, all cores secure, glands tight
10Insulation resistanceAbove the manufacturer's minimum, measured winding to earth
11Supply voltageWithin 10% of the nameplate value

Insulation resistance before filling is the one people skip. Once the tank is full, a low reading means draining it again to investigate. Test dry, record the figure, and compare it at the next service.

Float heights are covered in how to set float switch height.


Stage 2: first run

Now fill the tank and run the pump for the first time. Keep your hand near the isolator.

  1. Fill slowly through the normal inlets, not with a hose into the tank. You are testing the drainage, not just the pump.
  2. Watch the start level. The pump should start at the designed point. If it starts early or late, the float is wrong.
  3. Confirm the rotation on three-phase units. A momentary start is enough — check that flow appears at the discharge. If there is no flow or very little, swap two phases and retest. Running backwards for a few seconds does no harm; running backwards for an hour does.
  4. Watch the stop level. The pump should stop with the tank emptied and before the level falls to the motor.
  5. Time the run. A full tank should empty in a sensible time — not seconds, not minutes.
  6. Clamp the current while the pump is running and compare with the rating plate.
  7. Check the discharge. Flow should be steady and full-bore, with no surging.

Do not test run-dry protection by actually running it dry. Confirm instead that the stop float is set above the motor, and that the pump stops when the level reaches it. A deliberate dry run costs a mechanical seal.


Stage 3: three full cycles

One cycle proves the pump works. Three cycles prove the control works.

TestMethodPass criterion
Start / stop repeatabilityFill and empty three timesSame start and stop levels each time
BackflowMark the tank level immediately after the pump stops, check again in ten minutesNo rise
AlarmLift the alarm float by handAlarm sounds within a second or two
Leak checkInspect all joints, the lid, the glands and the dischargeNo weeping
VentListen at the vent termination during a pump runAir moves freely, no gurgling
NoiseListen at the pump and in the room aboveNo grinding, rattling or banging
Current stabilityClamp on the third cycleSame as the first, at or below rated

The backflow test is the one that catches the most installation errors. A non-return valve fitted backwards, missing, or of the wrong type for a vertical riser will pass every other test and fail this one. Mark the level, wait ten minutes, look again.


The record sheet

Fill this in and leave a copy with the installation. It is the only way to tell degradation from design later.

ItemRecorded value
Model and serial number
Date of commissioning
Supply voltage (measured, pump running)
Running current (measured, per phase)
Insulation resistance (before filling)
Start level (mm from tank base)
Stop level (mm from tank base)
Alarm level (mm from tank base)
Run time, full tank (seconds)
Discharge flow (estimated or measured)
Static lift (m)
Discharge bore (mm)
Non-return valve type
Alarm tested (Y/N)

Two years later, a running current that has risen 15% is a blocked impeller. Without the baseline, it is a guess.


Faults that show up at commissioning

Symptom at commissioningLikely cause
Pump will not startFloat not calling, wiring error, wrong voltage, capacitor
Pump starts immediately on power-upFloat set too high, or stuck up
Pump runs but no flowAir lock, closed valve, wrong rotation, non-return valve backwards
Flow is weakDischarge reduced, valve partly closed, wrong rotation
Trips the breaker on startInsulation fault, wrong wiring, undersized cable — see tripping the breaker
Trips after a few minutesOverload — see overheating
Level rises after the pump stopsNon-return valve — see water coming back up
Cycles rapidlyFloat differential too narrow — see short cycling
Alarm sounds on first fillAlarm float set below the start float
Smell in the roomTrap siphoned, or vent terminating wrongly

Handover

Commissioning is not finished until the person who will live with the station knows four things:

  1. Where the isolator is and how to switch it off.
  2. What the alarm means and what to do when it sounds — look in the tank before silencing it.
  3. What must not go down the drain — wipes, sanitary products, fat, cat litter.
  4. Who to call, and the model code.

A laminated card next to the panel with those four points prevents more damage than any amount of documentation left in a drawer.


Working on a real project?

Send the fixture list, not the model code

Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.

FAQ

How long should a lifting station run to empty a full tank? Long enough to be a sensible run time and short enough not to be a concern — typically tens of seconds for a domestic tank, not a couple of seconds. Record the figure at commissioning; it is the baseline for later comparison.

Do I need to test the alarm at commissioning? Yes. Lift the alarm float by hand and confirm the alarm sounds. It is the only component whose failure you will not notice until you need it.

Can I test run-dry protection by running the pump dry? No. Confirm the stop float is set above the motor instead. An actual dry run damages the mechanical seal, which is cooled and lubricated by the pumped liquid.

What current should the pump draw? At or below the figure on the rating plate, measured with the pump running at its normal duty. A figure clearly above it means the pump is overloaded; clearly below with no flow means it is not moving water.


Next step

If a new installation fails one of these checks, describe which one and what you measured. Most commissioning faults are installation errors rather than pump faults, and they are quick to identify once the measured values are known.