Nine steps from survey to handover — base, inlet fall, vent, discharge valve train, electrical supply, float levels and commissioning test.
Installing a external lifting station — also called a sewage lifting device, wastewater lifting station or sewage pumping station depending on the supplier — follows a fixed sequence: survey the position, set a level base, connect the inlet with adequate fall, run a full-bore vent to outside air, fit the discharge train with a non-return valve and isolation valve, connect the electrical supply, set the float levels, then commission and test. Skipping any one of those steps produces a station that works on the day and fails within a year.
Most installation failures are not pump failures. They are vent, fall, valve-access or level-setting failures — all of them avoidable with a checklist.
Before you start: the survey
Five things to establish before anything is delivered to site.
| Item | What to confirm |
|---|---|
| Position | Level floor, lid accessible for service, clear of traffic |
| Inlet route | Every fixture can reach the inlet with adequate fall |
| Discharge route | Vertical lift, horizontal run, bend count, bore available |
| Vent route | A path to outside air at full bore |
| Power | Isolator position, circuit capacity, RCD protection |
The two that stop jobs are the vent route and the discharge bore. Establish both before the station is ordered, not after it is on site.
Which type of station are you installing?
The installation sequence is the same for every type, but the base preparation is not.
| Type | Base requirement |
|---|---|
| Above-floor station | Sits on the finished floor; needs only a level, sound surface and a step or ramp if it is in a traffic route |
| Underfloor station | Set into a formed recess; the recess must be level and able to carry the filled weight |
| Buried sewage lifting station | Needs a compacted excavation, a surrounding drainage layer where groundwater is present, and a lid rated for the surface load |
| External sewage lifting station | Needs frost protection, a sealed lid and a discharge route that does not run back into the building |
| Compact / packaged station | Usually factory-assembled with the pump, floats and valve train already fitted; less site work, but confirm the inlet positions suit the layout before ordering |
A ready to connect or packaged sewage lifting station saves site time, but only if the inlets, discharge spigot and vent outlet all line up with what is already built. Check that before it is delivered.
Step 1: Prepare the base
A sewage lifting unit must sit level. On an uneven floor the tank distorts, the lid does not seal and the float can foul the casing.
- Clear and level the floor. A thin mortar bed or a levelling compound is usually enough.
- Confirm the base can carry the filled weight. A 460 L station full of wastewater is heavy, and the load is point-loaded through the tank base.
- If the station is to be buried, the excavation needs a compacted base and, where groundwater is present, a surrounding drainage layer.
Do not sit a station directly on a rough slab and rely on the weight to settle it. It will not settle evenly.
Step 2: Position the station and mark the connections
Set the station in place and mark the inlet, discharge and vent positions on the fabric of the building before making any permanent connection.
At this point check three clearances:
- Lid opening clears any obstruction by at least a hand's width.
- Inlet invert is low enough for the fixtures to reach it with fall.
- Discharge spigot aligns with the pipe route without adding an unnecessary bend.
Step 3: Connect the inlet
Inlet pipework runs by gravity from the fixtures to the station. Two rules:
- Maintain continuous fall. Soil pipework generally needs between about 1 in 40 and 1 in 110 depending on diameter and the applicable code — check the local requirement, but do not run level.
- Do not reduce the diameter to make the route easier. A reduced inlet becomes the governing restriction and the sewage lifting device blocks there, not at the pump.
Seal the inlet where it enters the tank. The grommet or sealant joint at this point is one of the most common sources of odour.
Step 4: Run the vent
This is the step most often skipped and the one that decides whether the wastewater lifting station smells.
The vent must run at full bore from the tank's vent outlet to outside air — above the roofline or through an external wall with a suitable terminal. It must not terminate in a roof void, a lightwell or a garage, and it must not be replaced by an air admittance valve.
Detailed routing guidance is in how to vent a sewage lifting station. The short version: full bore, no reductions, no dips, away from windows and air intakes.
Step 5: Build the discharge train
From the station's discharge spigot, in order:
pump discharge → isolation valve → non-return valve → discharge route to sewer
Requirements:
- Non-return valve above the tank's maximum water level, accessible, arrow pointing away from the pump.
- Isolation valve so the line can be shut before the non-return valve is serviced.
- Both reachable without removing fixed panels.
A non-return valve that cannot be reached is a valve that will never be cleaned, and an uncleaned valve short-cycles the pump for the rest of its life. See where to fit the non-return valve.
Step 6: Electrical connection
| Item | Requirement |
|---|---|
| Supply | Match the unit — 220–240 V / 50 Hz or 110 V / 60 Hz. The two platforms are not interchangeable |
| Isolation | A local isolator within sight of the station |
| Protection | RCD protection appropriate to the installation |
| Cable entry | Through the gland provided, sealed against moisture |
| Alarm | High-level alarm wired and tested if the unit has one |
Cable entry is where water gets in. A gland that is oversized, or a cable sheath stripped too far back, lets moisture into the terminal box and that is how windings fail two years later.
If the station is a submersible sewage lifting station — the pump sits in the tank, not beside it — the cable gland is the only barrier between the winding and the contents of the tank. Treat it as a sealed component, not as a cable entry.
Step 7: Set the float levels
Three levels matter:
| Level | Setting principle |
|---|---|
| Stop level | Low enough to empty the tank usefully, high enough to keep the impeller submerged |
| Start level | Below the inlet invert, so incoming wastewater does not back up before the pump starts |
| Alarm level | Above the start level, with enough buffer for someone to respond |
The working volume between start and stop should give a sensible cycle length. Too small and the pump short-cycles; too large and the tank holds wastewater longer than it should.
For a tethered float, cycle length is adjusted by tether length. For a vertical float, by the stop collars. Test by running water in and watching the pump start and stop.
Step 8: Commission
Run the station through a full cycle before handing over.
| Test | Pass criteria |
|---|---|
| Fill test | Pump starts at the set level, not before |
| Empty test | Pump stops with the impeller still submerged |
| Non-return valve | Water level holds after the pump stops; no drain-back |
| Vent | No gurgling, no odour, air moves freely at the terminal |
| Alarm | Triggers at the alarm level |
| Leak check | No weeping at inlet, discharge or lid gasket |
| Noise | No unusual vibration or rattle |
The non-return valve test is the one that catches most installation errors. Watch the tank for two minutes after the pump stops. If the level rises, the valve is passing or fitted backwards.
Step 9: Hand over
Give the building operator three things:
- The model code and the set levels, written down.
- The maintenance routine — float test monthly, impeller clear annually, valve check annually.
- What to do if the alarm sounds — and where the isolator is.
Most emergency call-outs are a stuck float that the operator could have freed in two minutes with a hand, if they had known to try.
The five mistakes that cause most call-backs
- No vent, or an air admittance valve instead of a vent. Odour, permanently.
- Non-return valve fitted backwards. Pump runs, nothing moves.
- Stop level set too low. Pump runs dry, seal fails.
- Inlet run without fall. Solids settle in the inlet pipe.
- Cable gland not sealed. Moisture ingress, winding failure in year two or three.
None of these are product faults, and all of them are visible at commissioning if someone checks.
Working on a real project?
Send the fixture list, not the model code
Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.
FAQ
How long does installation take? A straightforward retrofit of a compact sewage lifting station with an existing discharge route is typically a half to one day for one fitter. Running a new vent to outside air or a long discharge route extends it.
Can I install a lifting station myself? The mechanical work is within the scope of a competent DIYer in many jurisdictions, but the electrical connection and the discharge connection to a sewer usually require a qualified tradesperson and may require notification. Check the local rules.
Does the station need a concrete plinth? Not usually — a level, sound floor is sufficient. A plinth is used where the floor is uneven or where the station needs to be raised to meet the inlet fall.
What if there is no route for a vent? Then the installation has a design problem that no equipment choice solves. Options are a different station position or a different drainage strategy. Do not accept an air admittance valve as a substitute.
What is the difference between a sewage lifting station and a sewage pumping station? Very little in practice. Both lift wastewater that cannot drain by gravity. "Pumping station" is more often used for larger, sometimes buried installations serving several properties; "lifting station" or "lifting device" is more common for a single-building unit.
Can a sewage lifting unit be installed outdoors? An external sewage lifting station is available, but it needs frost protection, a sealed lid and a discharge route that cannot run back into the building. Confirm the ambient temperature range with the supplier before specifying one.
Next step
Send the fixture list, the available discharge bore and the height to the sewer connection. We will confirm the model, the connection set and the vent outlet size for that unit.
Request a quotation · See the model range
Related reading
- Submersible vs dry-installed stations — decide the arrangement before you start
- Flood-proofing a sewage lifting station — the two flood risks and which measures address them
- How to test a station after installation — the commissioning checks