Retrofitting a Sewage Lifting Station into an Existing Building

2026-11-108 min readInstallation and Commissioning

A retrofit has no allowance for anything: no space, no depth, no power, no discharge route. The three routes, and the three jobs that decide the outcome.

Retrofitting a sewage lifting station

A retrofit is harder than a new installation for one reason: nothing was allowed for.

In a new build, the chamber depth, the discharge route, the electrical supply and the vent are all part of the design. In a retrofit, every one of them is a problem to be solved inside a finished building, usually with a fixed budget and a date.

The three things that decide whether it works:

The discharge route. Where the pumped sewage can go, and at what level. The depth. Whether there is room below the floor for a chamber, or whether the unit has to sit above it. The electrical supply. How a dedicated circuit reaches the station through a finished building.

Get those three settled before ordering anything. Everything else follows.

Replacing an existing station is a different job with different constraints, and is covered in How to replace a sewage lifting station.


The five constraints

ConstraintWhat it means in a retrofit
SpaceThere is no plant room, so the unit goes under a floor, in a cupboard or outside
DepthThe slab may be shallow, suspended, or over a room that cannot be lost
DischargeThe pipe has to reach a gravity drain, through walls and floors that are already finished
PowerA dedicated circuit has to be run from the board to a wet location
VentThe vent has to reach atmosphere from a chamber that did not exist

Each of these is a design question in a new build. In a retrofit, each is a negotiation with the building.


Three retrofit routes

1. Floor-mounted unit in an existing space

A sewage lifting device that sits on the floor in a plant room, a cupboard or a utility space, with the fixtures draining into it by gravity.

Requires: a space at a level below the fixtures, and a discharge route from it. Avoids: cutting the floor, excavation, and the anti-flotation question. Best for: a basement with an unused corner, a garage, a utility room.

This is the easiest retrofit by a wide margin, and it is worth checking whether it is possible before considering anything else. The constraint is that the unit's inlet must be below the lowest fixture outlet — so the space has to be genuinely low, not just nearby.

2. Recessed chamber in the floor

A chamber set into the floor, with the cover finishing flush.

Requires: enough depth, a slab that can be cut, and a base. Avoids: losing floor space. Best for: bathrooms and wet rooms where a floor-standing unit is not acceptable.

The depth is the constraint. A shallow suspended slab may not allow a chamber of the required volume, and the alternative is a shallower chamber that short-cycles. See Installing a lifting station in a concrete floor.

3. External buried chamber

A chamber outside the building, with the fixtures draining out to it.

Requires: external space, excavation, and a gravity fall from the fixtures to the chamber. Avoids: taking space inside, and most of the noise. Best for: where the fixtures are near an external wall and the ground allows excavation.

The fall is the constraint: the fixtures have to reach the chamber by gravity, which means the chamber has to be low enough and close enough.


Comparing the three

Floor-mountedRecessed chamberExternal buried
Floor cuttingNoneYesNo, but external excavation
Space lost insideA cupboard or cornerNoneNone
Depth neededNoneChamber height plus baseChamber height plus base
Noise insideAudibleAudibleMinimal
Cost of the civil workLowestModerateHighest
ReversibleYesNoNo
Suits a listed or period buildingUsuallyRarelySometimes

The reversibility row matters more than people expect. A floor-mounted unit can be removed and the space returned to something else. A cut floor cannot.


The three jobs that decide it

The discharge route

This is the hardest part of most retrofits, and it is where budgets fail.

The discharge pipe is pressurised, so it can go up, along and through — but it has to reach a gravity drain or a manhole, and it has to terminate above that drain's flood level.

Typical routes: up through a cupboard to the floor above and out through a wall; horizontally through a wall to an external manhole; up an external wall in a protected pipe.

What makes it hard: the pipe has to be accessible for the non-return valve, it has to be protected from frost where it runs outside, and it has to be sealed where it passes through a wall. See Drilling and sealing pipe penetrations in a basement.

Establish this route before buying the station. A station bought before the route is known is a station that may not be installable.

The electrical supply

A dedicated circuit from the board to a wet location, with earth leakage protection and a means of isolation.

In a finished building this means a cable route through walls, floors and ceilings — and it is the item most often underestimated. See Does a sewage pump need a dedicated circuit.

The practical question: is there a spare way in the board, and is there a route from it to the station? If the answer to either is no, the electrical work becomes the critical path.

The vent

A chamber that did not exist has no vent, and a vent has to reach atmosphere.

Options: up an external wall to a high termination; into an existing vented soil stack, subject to conditions; up through the building to roof level.

The first is usually the cheapest in a retrofit, provided the wall is accessible and the termination is far enough from windows and intakes. See Connecting a lifting station to a soil stack.


Older buildings: what to expect

Unknown pipe materials. Existing drains may be pitch fibre, cast iron, asbestos cement or something unrecorded. Each has its own handling requirements, and asbestos cement in particular is a licensed removal in many jurisdictions.

No damp proof membrane or tanking. Cutting a floor in a building with no DPM creates a path for groundwater that did not exist before.

Shallow or no foundations under the slab. A chamber that needs a base may find nothing suitable to bear on.

Restricted access. Getting a chamber, a pump and a mini-excavator into a basement may not be possible, which changes the construction method entirely.

Listed or protected status. Cutting a historic floor or an original wall may need consent.

None of these is a reason not to do the work. All of them are reasons to survey before quoting.


Living with it during the work

A retrofit in an occupied building has a specific problem: the facilities stop working while the station is being installed.

Plan for it:

Sequence the work so the fixtures stay usable as long as possible. Connect the new station before disconnecting the old arrangement where possible.

Arrange temporary facilities. A temporary WC, or access to another part of the building.

Expect a day or two without the affected facilities. A floor-mounted unit can sometimes be installed in a day; a recessed chamber in a finished bathroom takes longer.

Protect the routes. Dust and damage along the discharge and cable routes is a common source of complaint, and it is avoidable with sheeting and a plan.


Acceptance checklist

Before the installer leaves:

  1. Every fixture drains freely into the station
  2. The pump runs and empties the chamber fully
  3. The pump stops at the correct level, without hunting
  4. The non-return valve holds — no return flow after the pump stops
  5. The alarm sounds and reaches someone
  6. The vent is connected and terminates correctly
  7. No odour in the room after a day of use
  8. No water at the floor around the chamber
  9. The isolation valve is accessible and operates
  10. The pump can be removed through the cover
  11. The electrical circuit is dedicated, protected and labelled
  12. The settings and the test results are recorded

Items 4, 9 and 10 are the ones that get skipped and the ones that matter at the first service.


Working on a real project?

Send the fixture list, not the model code

Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.

FAQ

Can I retrofit a lifting station without digging up the floor? Yes, if there is a space at a lower level — a plant room, a cupboard, a garage — where a floor-mounted unit can sit with the fixtures draining into it by gravity. That is the least invasive option.

How deep does the chamber have to be? Deep enough for the inlet to sit below the lowest fixture outlet with the required fall, and deep enough for the working volume. Both constraints apply, and the second is often the one that cannot be met in a shallow slab.

Where can the discharge go? To a gravity drain or manhole, terminating above its flood level. The route is usually the hardest part of the retrofit and should be established before the station is ordered.

Do I need a new electrical circuit? Almost always yes, and it should be dedicated with earth leakage protection. Running it through a finished building is often the longest part of the job.

How long does a retrofit take? It depends on the civil work, not the equipment. A floor-mounted unit in an existing space can be a day. A recessed chamber in a finished bathroom, with a new discharge route and a new circuit, is a small works project.


Next step

Send us photographs or a sketch of the space, the fixture positions, the level of the nearest drain, and where the electrical board is. We will tell you which of the three routes fits the building and what the critical path will be.

Request a quotation · See the range · Floor-mounted vs buried sewage stations


Still unsure? Message the engineer on WhatsApp.

Models referenced in this note