Inlet pipework needs a continuous fall in a defined band — too shallow and solids settle, too steep and the liquid outruns them. How to set, measure and check it.
Inlet pipework to a lifting station needs a continuous fall within a defined band — commonly between about 1 in 40 and 1 in 110, depending on pipe diameter and the code in force. Shallow falls let solids settle; very steep falls let the liquid run ahead of the solids and leave them behind. The target is a gradient that keeps the whole contents moving together.
The practical requirement is simpler than the number: continuous, in the right direction, with no level sections and no back-fall. Most failures are not a marginally wrong gradient — they are a section that runs uphill by a few millimetres because it crosses a joist.
Why the band exists
A gravity drain carries two things at once: liquid and solids. For the pipe to stay clear, they have to travel together.
Too shallow. Velocity falls below the self-cleansing threshold. Solids settle, the pipe silts up, and the blockage is inside a wall or under a floor. This is a slow failure that appears months after installation.
Too steep. The liquid accelerates ahead of the solids, leaving them stranded on the pipe wall. Counter-intuitively, a very steep drain can block. Some codes therefore specify a maximum gradient as well as a minimum.
In the band. The mixture moves as a body, fast enough to be self-cleansing, without the liquid separating from the solids.
Indicative gradients
| Pipe size | Typical fall range | Notes |
|---|---|---|
| Small bore (32–40 mm) | Around 1 in 40 to 1 in 60 | Smaller bores need steeper falls to stay clear |
| Soil pipe (100–110 mm) | Around 1 in 40 to 1 in 110 | The wider range reflects the code and the run length |
| Long runs | Upper end of the range | More length means more opportunity to settle |
These are indicative. Use the gradient specified by the code in force for your market, and for the specific pipe diameter — the values differ between jurisdictions and between pipe standards.
How to measure it
A fall of 1 in 40 means 25 mm of drop per metre. Over a 4 m run that is 100 mm total — a noticeable slope, not a token one.
Practical measurement:
- Establish the height of the station inlet centre above finished floor.
- Establish the height of the fixture outlet centre.
- Measure the horizontal distance between them.
- Check that the difference in height over that distance gives a gradient inside the band.
Then verify the installed pipe, not the design:
- Use a spirit level along the run, checking at several points.
- Watch for a low point where the pipe crosses a joist or changes direction.
- Check the pipe is supported at the intervals the material requires — unsupported pipe sags over time, and a sag is a low point.
The installed check matters because a correctly designed run is frequently installed with a small back-fall where it passes an obstruction.
The five ways inlet fall goes wrong
1. A level section. Often where the pipe passes through a wall or a boxing. Water stands in it, solids settle.
2. Back-fall over a joist. The pipe dips under and comes back up. A few millimetres is enough.
3. A sagging flexible connector. The most common single cause of a blocked toilet branch. The connector dips, holds water, and collects solids. Use a rigid connector, or support the flexible one so it cannot sag.
4. Unsupported pipe. Plastic pipe sags between clips over months, particularly when warm. Clip at the material's specified intervals.
5. Reduced diameter to make a route. The reduction becomes the restriction, and the fall becomes irrelevant because the pipe blocks at the narrow point.
Fall and the station inlet height
The inlet height on the station is fixed by the product. That fixes the maximum fall available from any given fixture.
If the fixture outlet is too low relative to the station inlet, there is no fall to be had, and no amount of pipe-laying skill creates one. The options are:
- A different station with a lower inlet.
- A different fixture position.
- A raised platform under the fixture.
- A macerating unit that accepts a low-level connection.
Establish this before the station is ordered. It is the single most common reason a retrofit stalls on site.
Fall on the discharge side is different
It is worth being clear that the fall requirement applies to the inlet — the gravity side.
On the discharge side, the pipe goes upward, driven by the pump. There is no fall requirement; there is a friction requirement instead. The discharge is sized on velocity and head loss, not on gradient — see how to choose discharge pipe diameter.
Confusing the two leads to odd decisions, such as trying to give the discharge pipe a fall.
Checking a completed installation
| Check | Method | Pass |
|---|---|---|
| Gradient | Spirit level at several points along the run | Continuous fall in the correct direction, within the band |
| Low points | Visual, at joist crossings and direction changes | None |
| Support | Check clip spacing against the material specification | No visible sag |
| Flexible connectors | Look for a dip | Straight and supported |
| Diameter | Check no reduction has been introduced | Unchanged from fixture to station |
| Flow test | Run water through and observe | No standing water, no gurgling |
The flow test is the practical confirmation: after running water through, there should be no standing water anywhere in the run.
Working on a real project?
Send the fixture list, not the model code
Send the fixture list, required lift height and supply voltage. We will recommend the matching model from the 2026 catalog.
FAQ
What is the minimum fall for a drainage pipe into a lifting station? Commonly around 1 in 40 for small-bore pipe, extending to about 1 in 110 for larger soil pipe. Use the gradient specified by the local code for the pipe diameter.
Can the fall be too steep? Yes. Very steep falls let the liquid run ahead of the solids and leave them behind. Some codes specify a maximum gradient for this reason.
How do I check the fall after installation? A spirit level at several points along the run, plus a visual check for low points at joist crossings and a flow test for standing water.
What if there is not enough height for a fall? The station inlet is too high for the fixtures. Options are a lower inlet, a raised platform, a different fixture position, or a macerating unit with a low-level connection.
Next step
Send the fixture outlet heights, the proposed station position and the horizontal distance between them. We will confirm whether the inlet height works and which model fits.
Request a quotation · Connect a toilet to a lifting device · See the range
Still unsure? Message the engineer on WhatsApp.